The MorainePlanning & Conservation Advisory

O. Reg. 41/24 · Conservation Authorities Act s. 28.1

2026 Conservation Authority permit fees on the Oak Ridges Moraine

Residential permit fee tiers from the published 2025/2026 schedules of all nine Conservation Authorities whose watersheds cross the Oak Ridges Moraine, with the completeness rules and review timelines that apply to every application.

Canada geese on a lily-covered kettle pond edged with cattails
O. Reg. 41/24 residential permit fee tiers — 9 Oak Ridges Moraine Conservation Authorities (2025/2026 schedules)
AuthorityKey Moraine municipalitiesEffective basisRoutine / minorStandard / intermediateMajor / complexInquiry, clearance & notes
TRCAToronto and Region Conservation AuthorityCaledon, Vaughan, King, Richmond Hill, Whitchurch-Stouffville, Pickering, Ajax, UxbridgeFee schedule effective Feb 1, 2026$560 (Minor)$1,045 (Standard)$1,490 (Major base) / $2,840 (Complex base) + technical reviewApplications through the PARES online portal; permit extensions 50% per year; commercial and subdivision files start at $2,555–$11,925+.
LSRCALake Simcoe Region Conservation AuthorityKing, Aurora, Newmarket, Whitchurch-Stouffville, East Gwillimbury, Uxbridge, Scugog, Bradford West Gwillimbury, InnisfilFee schedule effective Apr 1, 2026$624 (Routine) / $780 (Minor)$2,013 (Intermediate)$6,018 (Major — complex technical studies)Reviewed alongside the Lake Simcoe Protection Plan policies.
CVCCredit Valley ConservationCaledon, Mono, Erin, Orangeville2026 consolidated fee schedule$274 (Minor Works) / $561 (Small Development)$2,157 (Medium Development); $997–$7,191 wetland/watercourse (small–medium)$19,176 (Large) / $26,634 (Major Development); up to $30,896 major wetland/watercourseProperty / solicitor inquiry: $392 (incl. HST where applicable).
CLOCACentral Lake Ontario Conservation AuthorityUxbridge, Scugog, Whitby, Oshawa, ClaringtonCurrent O. Reg. 41/24 scheduleInquiry-scoped (about $250–$550 typical minor tier)Project-scoped through the CLOCA portalProject-scoped + technical reviewPre-consultation inquiry (about $200–$300 baseline) comes before formal fee confirmation.
GRCAGanaraska Region Conservation AuthorityClarington, Port Hope, Cobourg, Hamilton Township, Cavan MonaghanCurrent O. Reg. 41/24 schedule~$465 (Minor development or wetland/watercourse)~$675 (Standard development) / ~$1,185 (Standard wetland/watercourse)~$10,230 (Major development/watercourse); ~$6,710 bridge/culvertTitle / real estate inquiry about $255; extensions and minor amendments about $90.
NVCANottawasaga Valley Conservation AuthorityAdjala-Tosorontio, Mono, New Tecumseth, Mulmur2026 schedule (+3% cost-of-living adjustment)~$110–$573 (Letter approval / Minor tier)Tiered standard residential (confirmed at pre-consultation)Complex / major files scale into multi-thousand-dollar tiersWorks to 30-day minor / 90-day major review timelines.
KawarthaKawartha ConservationScugog, Kawartha Lakes, Clarington, BrockCurrent O. Reg. 41/24 schedule (Schedules 1 & 2)Streamlined minor permit (fee confirmed at inquiry)Standard residential permit (fee confirmed at inquiry)Major / technical review permit (fee confirmed at inquiry)Pre-consultation about $200–$300; requires proof of ownership dated within 6 months.
Lower TrentLower Trent ConservationBrighton, Cramahe, Alnwick/Haldimand, Trent Hills, Quinte WestCurrent O. Reg. 41/24 schedule$100 (Routine/Drainage) / $235 (Minor)$590 (Standard)$850+ (Complex base + technical review)Unauthorized works incur 2×–3× the base permit fee.
OtonabeeOtonabee ConservationCavan Monaghan, Otonabee-South Monaghan, Peterborough, SelwynCurrent O. Reg. 41/24 schedule$405 (Minor flood/erosion) / $545 (Minor wetland/shoreline)$1,145–$1,265 (Intermediate)$2,120–$2,240 (Major)Real estate / legal inquiry $140; proposal inquiry $315; unauthorized work 2×–3× penalty.

Sources: each authority's published O. Reg. 41/24 fee schedule (effective basis shown per row). "~" marks a figure rounded from the schedule; "fee confirmed at inquiry" means the authority sets the fee after a pre-consultation inquiry. HST is extra unless the schedule states otherwise. See Sources & Methodology.

What an O. Reg. 41/24 permit covers

Since April 1, 2024, Ontario Regulation 41/24 (Prohibited Activities, Exemptions and Permits) has replaced the individual Section 28 regulations each Conservation Authority used to administer. A permit is required for development in hazard lands and their allowances — flooding, erosion, dynamic beaches and unstable soil or bedrock — and in or near wetlands, and for any alteration of a river, creek, stream or watercourse. Permits are now limited to those natural hazard and wetland interests; they sit alongside, not instead of, the Oak Ridges Moraine Conservation Plan tests applied by the municipality.

On the Moraine that means most estate and rural files deal with two separate sets of rules: the ORMCP (designation, Section 6/7 rights, 30 m and 120 m feature tests, Section 30 landform caps) through the municipal planning and building process, and the Conservation Authority permit for anything inside a regulated area.

How the fee tiers map to real projects

TierTypical residential worksUsual review target
Routine / minorSmall additions, decks, accessory buildings, pools and minor grading outside the hazard itself; works that need no technical report.30 days from a complete application
Standard / intermediateA new dwelling or substantial addition within a regulated allowance, septic replacement near a watercourse, fill placement with a grading plan.30–90 days depending on technical review
Major / complexWorks requiring a slope stability, floodplain, hydrogeological or wetland impact study; watercourse crossings; multi-lot or commercial site plans.90 days from a complete application

Authorities classify a file by their own schedule, so the same project can fall into different tiers in different watersheds. The ORMCP Screening Tool assigns a tier from the project type, the distance to features and the landform category, then reads the matching fee for the watershed you choose.

Completeness: when the clock starts

Under Section 7 of O. Reg. 41/24 an application is not complete until the authority has every required study, plan and the full fee. The authority has 21 days to tell the applicant whether the application is complete. Once complete, review targets are commonly 30 days for minor and 90 days for major applications. The fastest way to lose a season is to file without the studies the authority asked for at pre-consultation.

Unauthorized work. Where works start before a permit is issued, authorities commonly charge two to three times the base permit fee (Lower Trent and Otonabee state 2×–3× in their schedules), on top of any restoration order or prosecution under the Conservation Authorities Act.

Inquiries, clearances and extensions

  • Property / solicitor inquiries confirm whether a lot is regulated and whether outstanding violations exist: CVC $392, GRCA about $255, Otonabee $140 (real estate / legal) — useful before waiving conditions on a purchase.
  • Pre-consultation inquiries fix the scope and the fee before filing: CLOCA and Kawartha about $200–$300; Otonabee proposal inquiry $315.
  • Extensions and amendments: TRCA charges 50% of the permit fee per year of extension; GRCA about $90 for an extension or minor amendment.

Which authority regulates your property

Watershed boundaries, not municipal boundaries, decide the authority. King Township, Uxbridge and Whitchurch-Stouffville each straddle two or three watersheds (TRCA, LSRCA and, in Uxbridge, CLOCA); Caledon sits across TRCA and CVC; Clarington across CLOCA, GRCA and Kawartha. Check the authority's regulation mapping for the exact parcel — a property inquiry settles it in writing.

Permit fees are the smallest line

For most Moraine custom homes the Conservation Authority fee is a fraction of the soft costs. A Natural Heritage Evaluation typically runs $15,000–$40,000+, a hydrogeological assessment and water balance $10,000–$35,000+, a landform conservation plan with grading and stormwater design $8,000–$25,000+, and planning consultant fees $8,000–$45,000+ depending on the application stream. See the practice areas for what triggers each study.

References: Conservation Authorities Act, R.S.O. 1990, c. C.27, ss. 28–28.1; O. Reg. 41/24, s. 7; 2025/2026 fee schedules of TRCA, LSRCA, CVC, CLOCA, GRCA, NVCA, Kawartha Conservation, Lower Trent Conservation and Otonabee Conservation.

Before you buy, design or apply

Know what the Moraine will ask of your property

A pre-consultation site screening sets out the ORMCP designation, the Conservation Authority permit tier, the technical studies the municipality will require and a realistic soft-cost budget and timeline.