What an O. Reg. 41/24 permit covers
Since April 1, 2024, Ontario Regulation 41/24 (Prohibited Activities, Exemptions and Permits) has replaced the individual Section 28 regulations each Conservation Authority used to administer. A permit is required for development in hazard lands and their allowances — flooding, erosion, dynamic beaches and unstable soil or bedrock — and in or near wetlands, and for any alteration of a river, creek, stream or watercourse. Permits are now limited to those natural hazard and wetland interests; they sit alongside, not instead of, the Oak Ridges Moraine Conservation Plan tests applied by the municipality.
On the Moraine that means most estate and rural files deal with two separate sets of rules: the ORMCP (designation, Section 6/7 rights, 30 m and 120 m feature tests, Section 30 landform caps) through the municipal planning and building process, and the Conservation Authority permit for anything inside a regulated area.
How the fee tiers map to real projects
| Tier | Typical residential works | Usual review target |
|---|---|---|
| Routine / minor | Small additions, decks, accessory buildings, pools and minor grading outside the hazard itself; works that need no technical report. | 30 days from a complete application |
| Standard / intermediate | A new dwelling or substantial addition within a regulated allowance, septic replacement near a watercourse, fill placement with a grading plan. | 30–90 days depending on technical review |
| Major / complex | Works requiring a slope stability, floodplain, hydrogeological or wetland impact study; watercourse crossings; multi-lot or commercial site plans. | 90 days from a complete application |
Authorities classify a file by their own schedule, so the same project can fall into different tiers in different watersheds. The ORMCP Screening Tool assigns a tier from the project type, the distance to features and the landform category, then reads the matching fee for the watershed you choose.
Completeness: when the clock starts
Under Section 7 of O. Reg. 41/24 an application is not complete until the authority has every required study, plan and the full fee. The authority has 21 days to tell the applicant whether the application is complete. Once complete, review targets are commonly 30 days for minor and 90 days for major applications. The fastest way to lose a season is to file without the studies the authority asked for at pre-consultation.
Unauthorized work. Where works start before a permit is issued, authorities commonly charge two to three times the base permit fee (Lower Trent and Otonabee state 2×–3× in their schedules), on top of any restoration order or prosecution under the Conservation Authorities Act.
Inquiries, clearances and extensions
- Property / solicitor inquiries confirm whether a lot is regulated and whether outstanding violations exist: CVC $392, GRCA about $255, Otonabee $140 (real estate / legal) — useful before waiving conditions on a purchase.
- Pre-consultation inquiries fix the scope and the fee before filing: CLOCA and Kawartha about $200–$300; Otonabee proposal inquiry $315.
- Extensions and amendments: TRCA charges 50% of the permit fee per year of extension; GRCA about $90 for an extension or minor amendment.
Which authority regulates your property
Watershed boundaries, not municipal boundaries, decide the authority. King Township, Uxbridge and Whitchurch-Stouffville each straddle two or three watersheds (TRCA, LSRCA and, in Uxbridge, CLOCA); Caledon sits across TRCA and CVC; Clarington across CLOCA, GRCA and Kawartha. Check the authority's regulation mapping for the exact parcel — a property inquiry settles it in writing.
Permit fees are the smallest line
For most Moraine custom homes the Conservation Authority fee is a fraction of the soft costs. A Natural Heritage Evaluation typically runs $15,000–$40,000+, a hydrogeological assessment and water balance $10,000–$35,000+, a landform conservation plan with grading and stormwater design $8,000–$25,000+, and planning consultant fees $8,000–$45,000+ depending on the application stream. See the practice areas for what triggers each study.
References: Conservation Authorities Act, R.S.O. 1990, c. C.27, ss. 28–28.1; O. Reg. 41/24, s. 7; 2025/2026 fee schedules of TRCA, LSRCA, CVC, CLOCA, GRCA, NVCA, Kawartha Conservation, Lower Trent Conservation and Otonabee Conservation.