Why the Moraine asks about water
The Moraine's sands and gravels absorb rain and snowmelt and release it slowly to aquifers, springs, seepage areas and streams. The ORMCP protects that function through three groups of rules:
- Water conservation and water budgets (s. 24): development should keep pre- and post-development infiltration in balance and protect the quantity and quality of groundwater and surface water.
- Key hydrologic features and hydrological evaluations (s. 26): development within 120 m of a stream, wetland, kettle lake or seepage area needs a hydrological evaluation proving no adverse effect, and the 30 m minimum vegetation protection zone applies.
- Areas of high aquifer vulnerability and wellhead protection (ss. 27–29): certain uses are restricted where contamination could reach drinking water, and Wellhead Protection Areas (WHPAs) under source water protection plans add their own policies.
When a hydrogeological study is triggered
| Situation | Typical requirement |
|---|---|
| New custom home on private well and septic | Scoped water balance; well and septic suitability; sometimes nitrate attenuation |
| Any development within 120 m of a key hydrologic feature | Hydrological evaluation under s. 26 |
| Lot severance (two lots on private services) | Full hydrogeological assessment: well yield and quality, septic impact on both lots |
| Commercial, institutional or site plan development | Water budget, LID stormwater design, monitoring wells |
| Large impervious area or site in a Landform Conservation Area | Infiltration analysis tied to the Section 30 limits |
| Property inside a Wellhead Protection Area | Source protection screening; restricted activities review |
The water balance, in plain terms
Most Moraine water balances use the Thornthwaite-Mather method. It estimates how much of each year's precipitation evaporates, how much runs off and how much infiltrates, based on climate data, soil type, slope and land cover. The hydrogeologist calculates infiltration for the site as it is today and as it will be after construction, then designs measures so the "after" number does not fall short:
- roof leaders directed to soakaway pits or infiltration galleries;
- permeable interlocking pavers instead of asphalt on driveways and parking pads;
- infiltration trenches, bioswales and rain gardens sized to the soils;
- keeping native vegetation and topsoil depth outside the building envelope.
Link to landform. The same impervious areas that drive the water balance count toward the Section 30 impervious cap. Test the layout in the Landform Calculator before the hydrogeologist models it.

Fieldwork: wells, boreholes and monitoring
A desktop water balance may be enough for a small single-lot file. Larger files and anything near a key hydrologic feature usually need field evidence:
- Background review: provincial water well records, the Oak Ridges Moraine Groundwater Program (ORMGP) database, geology and source protection mapping.
- Boreholes and test pits: soil logs and groundwater levels; percolation (T-time) for septic design.
- Monitoring wells: seasonal groundwater levels, especially where basements, septic beds or ponds are close to the water table.
- Slug or pumping tests: aquifer properties and well yield; required for many severances.
- Water quality sampling: potability of a new well and baseline nitrate.
Septic systems and nitrate attenuation
Most rural Moraine homes rely on private septic systems, designed under the Ontario Building Code. On the Moraine the hydrogeologist may also be asked to show that nitrate from the system will be diluted to acceptable levels at the property boundary, and in sensitive aquifers a tertiary treatment unit may be recommended. Septic beds and mantles also count as disturbed area for landform purposes.
Typical cost
| Scope | Typical range |
|---|---|
| Scoped single-lot water balance and septic review | $8,000 – $15,000 |
| Hydrological evaluation near a key hydrologic feature | $12,000 – $25,000 |
| Severance or multi-lot assessment with boreholes, monitoring and pumping tests | $20,000 – $35,000+ |
| Commercial / site plan water budget with LID design support | $20,000 – $35,000+ |
Drilling, laboratory analysis and multiple monitoring rounds are the main cost drivers. Conservation Authority permit fees are separate; see the 2026 fee comparison.
Reading a hydrogeology checklist item
Pre-consultation checklists often list hydrogeology in shorthand. In practice the wording usually means:
- "Hydrogeological assessment" — well and septic suitability, groundwater levels and, for severances, both lots.
- "Hydrological evaluation" — the s. 26 study for a key hydrologic feature within 120 m.
- "Water balance" or "water budget" — pre- and post-development infiltration under s. 24, typically Thornthwaite-Mather.
- "Source water protection screening" — confirmation of whether the property lies in a WHPA or other vulnerable area under the local source protection plan.
A single P.Geo. report can often cover several of these if it is scoped properly at the start.
How we coordinate it
We scope the hydrogeology together with the NHE and landform design so fieldwork is done once, the water balance reflects the final site layout and the planning report can rely on both. The Screening Tool shows when hydrogeology is likely to be required for your project type and distance to features.
Sources: O. Reg. 140/02, ss. 24, 26, 27, 28 and 29; Clean Water Act, 2006 source protection plans; Ontario Building Code (Part 8, sewage systems); ORMGP. Figures are planning ranges; scope is confirmed at municipal and CA pre-consultation. See methodology.
